The Unit Availability and Capacity Factors are as follows:
|
|
December 2025 |
Year-to-Date |
|
Availability Factor (AF) |
29.38% |
50.72% |
|
Capacity Factor (CF) |
11.43% |
18.04% |
For the 2025 operating year, below is the monthly generation data and historical average monthly generation data for the project. As of December 2025, the Berkshire Wind Power Project completed 176 months of operation.
Throughout the month of December, total production from Berkshire Wind Phase 1 was 1,275.52 MWh. This is significantly lower than the historical average for the month of December, 3,036.2 MWh. This decrease in production was due to lower project availability.


Berkshire Wind Phase II
The Unit Availability and Capacity Factors are as follows:
|
|
December 2025 |
Year-to-Date |
|
Availability Factor (AF) |
72.90% |
94.51% |
|
Capacity Factor (CF) |
39.84% |
45.24% |
For 2025 operating year, below is the monthly generation data for the project. As of December 2025, the Berkshire Wind Phase 2 project completed 75 months of operation.
Throughout the month of December, total production from Berkshire Wind Phase 2 was 1,363.34 MWh. This is significantly higher compared to our historic December average of 1,011.2 MWh. Higher generation is due to this month continuing to have exceptionally high availability as it has for the past nine months.