Operations

 

 

 

 

 

 

 

 

 

 

 

 

 

Berkshire Wind Phase I

The Unit Availability and Capacity Factors are as follows:

 

   January 2026

    Year-to-Date

Availability Factor (AF)

        31.29%

         31.29%

Capacity Factor (CF)

         12.74%

         12.74%

For the 2026 operating year, below is the monthly generation data and historical average monthly generation data for the project. As of January 2026, the Berkshire Wind Power Project completed 177 months of operation.

  • Average Capacity Factor for the month of January since COD: 33.97%
  • Capacity Factor since COD: 22.04%

Throughout the month of January, total production from Berkshire Wind Phase 1 was 1,422.21 MWh. This is significantly lower than the historical average for the month of December, 2,936.1 MWh. This decrease in production was due to lower project availability.  

Berkshire Wind Phase II

The Unit Availability and Capacity Factors are as follows:

 

  January 2026

     Year-to-Date

Availability Factor (AF)

       87.83%

          87.83%

Capacity Factor (CF)

        49.97%

          49.97%

For 2026 operating year, below is the monthly generation data for the project. As of January 2026, the Berkshire Wind Phase 2 project completed 76 months of operation.

  • Average Capacity Factor for the Month of January since COD: 39.48%
  • Capacity Factor since COD: 32.25%

Throughout the month of January, total production from Berkshire Wind Phase 2 was 1,710.24 MWh. This is significantly higher compared to our historic January average of 1,209.6 MWh. Higher generation is due to this month continuing to have exceptionally high availability as it has for the past 10 months.