Operations

 

 

 

 

 

 

 

 

 

 

 

 

 

Berkshire Wind Phase I

The Unit Availability and Capacity Factors are as follows:

 

  December 2022

 Year-to-Date

Availability Factor (AF)

        47.52%

          71.75%

Capacity Factor (CF)

         24.55%

          24.66%

For the 2022 operating year, below is the monthly generation data and historical average monthly generation data for the project. As of December 2022, the Berkshire Wind Power Project completed 140 months of operation.

  • Average Capacity Factor for the month of December since COD: 38.85%
  • Capacity Factor since COD: 33.40%

Through the month of December, total production from Berkshire Wind Phase 1 was 2,739.2 MWh. This was lower than our historical average monthly production of 3,376 MWh. This decrease in production was due to decreased availability.

Berkshire Wind Phase II

The Unit Availability and Capacity Factors are as follows:

 

  December 2022

 Year-to-Date

Availability Factor (AF)

       47.55%

          66.36%

Capacity Factor (CF)

         34.84%

          26.64%

For 2022 operating year, below is the monthly generation data for the project. As of December 2022, the Berkshire Wind Phase 2 project completed 40 months of operation.

  • Average Capacity Factor for the Month of December since COD: 22.27%
  • Capacity Factor since COD: 11.75%

Through the month of December, total production from Berkshire Wind Phase 2 was 1,192.3 MWh. This was was average compared to our historical average monthly production of 1,212.3 MWh.