Operations

 

 

 

 

 

 

 

 

 

 

 

 

 

Berkshire Wind Phase I

The Unit Availability and Capacity Factors are as follows:

 

 March 2025

 Year-to-Date

Availability Factor (AF)

        50.41%

          51.96%

Capacity Factor (CF)

         23.04%

         22.76%

For the 2025 operating year, below is the monthly generation data and historical average monthly generation data for the project. As of March 2025, the Berkshire Wind Power Project completed 169 months of operation.

  • Average Capacity Factor for the month of March since COD: 31.03%
  • Capacity Factor since COD: 22.30%

Throughout the month of March, total production from Berkshire Wind Phase 1 was 2,572.3 MWh. This was lower than the historical average monthly production of 2,966.59 MWh. This decrease in production was due to decreased availability. 

      Berkshire Wind Phase II

The Unit Availability and Capacity Factors are as follows:

 

 March 2025

 Year-to-Date

Availability Factor (AF)

       82.87%

          88.52%

Capacity Factor (CF)

        37.62%

          53.21%

For 2025 operating year, below is the monthly generation data for the project. As of March 2025, the Berkshire Wind Phase 2 project completed 69 months of operation.

  • Average Capacity Factor for the Month of March since COD: 38.45%
  • Capacity Factor since COD: 30.55%

Throughout the month of March, total production from Berkshire Wind Phase 2 was 1,287.6 MWh. This was slightly higher than our historical monthly production of 1,222.95 MWh. This increase in production is due to increased availability.