Operations

 

 

 

 

 

 

 

 

 

 

 

 

 

Berkshire Wind Phase I

The Unit Availability and Capacity Factors are as follows:

 

  October 2021

 Year-to-Date

Availability Factor (AF)

        85.66%

          76.93%

Capacity Factor (CF)

         29.22%

          24.00%

For the 2021 operating year, below is the monthly generation data and historical average monthly generation data for the project. As of October 2021, the Berkshire Wind Power Project completed 125 months of operation.

  • Average Capacity Factor for the month of October since COD: 36.20%
  • Capacity Factor since COD: 34.25%

Through the month of October, total production from Berkshire Wind Phase 1 was 3,261 MWh. This was lower than our historical average monthly production of 3,755 MWh. 

Berkshire Wind Phase II

The Unit Availability and Capacity Factors are as follows:

 

  October 2021

 Year-to-Date

Availability Factor (AF)

       83.18%

          88.42%

Capacity Factor (CF)

         15.00%

          26.51%

For 2021 operating year, below is the monthly generation data for the project. As of October 2021, the Berkshire Wind Phase 2 project completed 25 months of operation.

  • Average Capacity Factor for the Month of October since COD: 21.02%
  • Capacity Factor since COD: 35.04%

Through the month of October, total production from Berkshire Wind Phase 2 was 513 MWh. This was lower than our historical average monthly production of 925 MWh.