As of December 31, 2018 the Berkshire Wind Power Project completed 91 months of operation.

The operating statistics as of December 31st  were:

Capacity factor since COD –  36.6%

Capacity factor for the past 12 months –  34.5%

The December 2018 capacity factor of 31.7% is well below average for the month. The average capacity factor for the month of December since COD is 46.2%.

Availability factor for December – 72.97%

Availability factor for the past 12 months – 90.81%